He added that the airport will re-open April 19.
Sirika disclosed this during a media tour led by the
Minister of Information and Culture, Alhaji Lai Mohammed.
“The contractor has been fully mobilized and he has done as
much as 57 per cent of the work, which is good and it shows that we are on
course”, Sirika explained.
“It also shows that we are on time and it means that we are
doing what we are supposed to do to ensure that the runway is opened come April
19.
“As you could see, this is brand new asphalt being laid and
it is finished and we have also gone far into the third part of the runway.
“If you go over there you will also see that we have started
the middle light of the runway. So we are doing the work simultaneously.
“We have even started the lightening with the cutting and
channels for the wires and we will continue so that we complete and achieve the
target given.
“The central light up installation commenced on Tuesday and
now they have gone far and as we progress, we will continue towards the runway
022,“ he said.
The minister explained that the first segment which is 1.2
kilometers has been completed, while asphalt was being laid on the second segment
of 2.4 kilometers.
He also disclosed that the runway was being rebuilt with new
and improved technology known as the Glass Fibre Grid to give it strength and
prevent it from cracking.
According to him, this is the first time that a Nigerian
runway is being treated with such material and the material is 50 toners to
cover the entire runway.
“We are on course and I am glad to say so because this
airport will be reopened with the terminal building wearing a new look.
“The closure of this airport also means that we will improve
on the terminal to make it more robust and create a seamless flow of
international and local passengers.
“The airport will be more compliant with the International
Civil Aviation Organisation standard and best practices and will be more
efficient at the time it is going to be reopened,’’ he said.
Sirika also disclosed that about 50 international flights
had been operated out of Kaduna airport with about 4,000 international
passengers within three weeks.